Project 3 Update 2

Boardwalk scrap removal started out well. With a little ingenuity we were able to transport loads of scrap right into the dumpster, little hand work. Moving right along and half done with the 1st dumpster by 9:30. Oops, we have a flat tire on the tractor. Had to know with all the old boards and nails we would find one sooner or later. Luckily it was on the front(smaller tires). Quick trip to shop for proper tools, then to town, tire repaired, back in business by lunchtime. Dumpster full before the end of the day.

Other things to do`

With plumbing fittings and dumpsters not available due to the severe weather, we moved on to another task. Seems there are trees blocking some trails at the Hudson Woods unit. Bob and I traveled all the trails within the unit and found 5 trees blocking or partially blocking trails. 1st priority was to remove the trees and reopen the trails. Then we returned to complete trimming the trails to facilitate hiking and mowing. Things grow so fast here the trails seem to close up within a couple of years. They have an “invasive” orange plant with 2 inch+ thorns that makes greenbriers and dewberry seem like a mild distraction.

Not ready for real cold

The forecast was for temperatures to get as low as 15F here along the Gulf shore and even colder inland.  We spent some time winterizing the refuge buildings and re-acquainting with shut-offs.  Finding winterization supplies was a real challenge since everyone needed them.  The forecast temps were about right but the added freezing rain/sleet and snow just shut the region down for several days. NO snow removal equipment.  The electric outage started in the middle of Sunday night with the temp around 15.  Stayed below freezing all day Monday and back down to 15F Monday night.  Lots of places started getting really cold really quick.  I even had to get up in the middle of the night and push the generator start button.  Electric was pretty intermittent from Monday thru Thursday.  At one point nearly half of Texas was without power. It warmed enough on Tuesday to expose a couple of frozen/burst refuge water pipes which we patched Wednesday.  We will need some additional fittings to repair permanently but, we restored water to the complex.

Things were really good here based on the Houston and Dallas news reports. Thousands of homes (4,900+ in Houston) have reported broken pipes and the city lost control of water pressure leading to water shortages and boil orders. They are going to be cleaning this up for a year.

As we discussed here in the Volunteer Village, “it is a good time to live in a self-contained RV”.

Project 3 update

We finished the removal of (5) boardwalk sections and moved all the scrap materials through the woods near the road, ready for dumpsters.  40 stacks my guess is 3 dumpsters.  We finished the work to date in 16 man-days so far.  Then we spent a week repairing the remaining 600 feet.  It is now ready for the public.  Looking forward to getting the dumpsters and wrapping it up.

Project 3

One of the larger projects for this season is the removal of another set of degrading boardwalks.  They are quite old and have become structurally unsafe.  Bob(another resident volunteer) and I start efforts and made good progress the 1st week using a different approach. We are disassembling in place rather than moving sections to the dumpster for disassembly.  Bob came up with a design for a board removal prybar that both expedited the process and saved our backs. The length of the boardwalks is about the same as our earlier project which consumed 27 man-days.  We should be done is about ½ that time using the new approach, even with an additional 1/3 of a mile from the boardwalk to the dumpster for disposal.

Lockdown

As a result of the attack on the capital, the refuge was placed into lockdown for Inauguration week. That limited our work to an area around the office and maintenance shop behind the locked gates.  Work for the week was limited to cleaning and organization of a steel storage rack, flower bed and maintenance building.

Back to Work

Project 2 at the refuge, rebuilding an overwater observation deck damaged when a tree fell on it.  With materials ordered and delivered during the holiday break Bob(another resident/volunteer at San Bernard) and I started on Monday Jan 4.  It took quite a while to gather the required tools and repair trailer lights prior to traveling to the worksite. It took a 6 ½  days but the finished product will be around for many years to come.

Week One

Two young bobcats bound across just ahead of us as we head for our first assignment, trimming along the newly expanded Bobcat boardwalk.  It is like watching a pair of adorable pet kittens.  Nice.  This trail is a great walk through the wetlands and actually in pretty good shape so we finish up in just a few hours.

Boardwalk removal

The first three days we dive into a demolition project at one of the remote refuge parcels, Hudson Woods.  A group of 6 younger volunteers with The Corp of Engineers provide extra muscle to remove then load into four roll-off dumpsters a 290 yard long boardwalk. It has been on the to-do list here for a while so everyone is glad to see it done.  We are off to a pretty good start.

Settling in

December 1 at San Bernard NWR.  The cloud of Covid hangs over even this remote spot as we start with a week-long quarantine/pre-work break.  I need the time to work on ornaments and other Christmas prep so it’s not all bad.  We report to work Dec 7.