Project 3 update

We finished the removal of (5) boardwalk sections and moved all the scrap materials through the woods near the road, ready for dumpsters.  40 stacks my guess is 3 dumpsters.  We finished the work to date in 16 man-days so far.  Then we spent a week repairing the remaining 600 feet.  It is now ready for the public.  Looking forward to getting the dumpsters and wrapping it up.